Excavating Lift pit
Excavated and installed underpinning to structural engineers sequence.
Excavated lift pit completed by our Hybrid 3phase electric excavator and muck moved by electric pump trucks.
Installed fixed steel reinforcement and form work completed in preparation for concrete pouring.
Preparation for installation of Water Management System: Excavation of 500lm of track around perimeter of building 280+ tonne of muck removed Shuttered and concreted 500lm drainage channel with 15nr sumps